Building Inspections
Inspections
- Building inspectors are available to address questions/ issues related to building permits and inspections from 8:00 a.m. - 9:00 a.m. or from 4:00 p.m. - 5:00 p.m.
- A pre-construction meeting is required for all residential and commercial building permits and must be scheduled before the permit is issued.
- Morning inspections will be between 9:00 a.m. – 11:00 a.m. Afternoon inspections will be between 2:00 p.m. – 4:00 p.m.
- Exact times for inspections will not be given.
- For any inspection that is turned down, a $50 re-inspection fee must be paid prior to the scheduling of a re-inspection.
Building Codes
- International Building Code, 2018 ed.
- International Fuel Gas Code, 2018 ed.
- International Mechanical Code, 2018 ed.
- International Plumbing Code, 2018 ed.
- National Electrical Code, 2020 ed.
- International Fire Code, 2018 ed.
- International Energy Conservation Code, 2015 ed.
- International Residential Code, 2018 ed.
- International Property Maintenance Code, 2018 ed.
- International Existing Building Code, 2018 ed.
- National Green Building Standard, 2008 ed.
- International Swimming Pool and Spa Code, 2018 ed.
- NFPA 101 Life Safety Code, 2018 ed.
- ADA Standards for Accessible Design, 2010 ed.
- 2016 NFPA 72 National Fire Alarm and Signaling Code
Required Inspections
- Driveway and Culvert – Driveway location and/or culvert size must be approved by the Morgan County Roads and Bridges Department. If the driveway and/or culvert are located on a State highway then approval from Georgia DOT is required. Driveway and culvert must be installed per specifications prior to any inspections. The driveway must be, at a minimum, graveled to the building site.
- Erosion, Sediment and Pollution Control – Erosion control devices must be installed prior to disturbance on all building sites where land disturbance will occur. If the building site is located within 200 feet of “State Waters” (Streams, Creeks, Rivers, Lakes, Ponds, Wetlands, or over 1 acre of disturbance), an Erosion, Sediment and Pollution control Plan must be submitted. All devices must be installed per the Manual for Erosion and Sediment control in Georgia (Green Book).
- Temporary Power Pole – All receptacles must be GFCI protected in a wet location enclosure, with an 8 foot ground rod(s) with Acorn clamp(s), and must be properly braced. All electrical parts must be in good working order and installed per the National Electrical Code.
- Footing – Size of footing will depend on size of structure. Minimum size is 8 inches thick by 16 inches wide. Minimum depth of 12 inches below undisturbed soil. All rebar must be tied and on chairs. Footings must be inspected before the concrete is poured. All work must be complete for an inspection. Only steel grade stakes are allowed in footing. Electrical bonding will also be inspected at this time. (NEC 250.50)
- Foundation Wall– Size and placement of vertical and horizontal bars according to code.
- Under Slab Plumbing – All work must be complete with a water and/or air test on all drain and supply lines per International Plumbing Code.
- Under Ground Electrical – All work must be installed per the National Electrical Code. Slab - All preparation (gravel, moisture barrier, wire, rebar, grade beams, etc.) must be complete for inspection. All slabs must have anchor bolts or straps installed per IRC One and Two Family Dwelling Code or manufacture’s recommendation.
- Slab- All ground, vapor barrier, wire if used, grade beams, and rebar must be complete for this inspection. Inspection must be complete to pouring concrete.
- Exterior Building Envelope – This inspection is prior to installing the exterior wall covering (siding, brick, etc.) and the Rough-in inspection. The water resistive barrier and all flashing around windows and doors must be complete for this inspection.
- Rough- in– All Framing, Electrical, Plumbing, and HVAC rough-in work must be complete. Must have air and/or water air test on all plumbing.
- Insulation–All insulation and caulking must be complete and installed per International Energy Conservation Code. (Exterior corners, tees, bottom plates must be caulked; all penetrations through the floor and ceiling and top and bottom plates must be sealed).
- Final Electrical- All electrical work must be complete with devices installed. All switch, receptacle and circuit breaker panel covers must be removed for this inspection.
- Certificate of Occupancy –Mandatory for all new homes or changes in occupancy. All work must be completely finished and ready to occupy. The electricity must be on for this inspection.
- Certificate of Completion - Mandatory for all remodels, additions, and non- habitable structures before the space can be occupied. All work must be completely finished and ready to occupy.
Please Note for #13 and #14:
- You will need two of the Energy Efficiency Certificates. One must be attached to panel box, and the other must be submitted to our office. The certificates need to be completely filled out.